Concrete volume for a slab or footing, the weight, and the cement, sand and aggregate to mix it yourself.

Concrete is ordered by the cubic metre and mixed by the part, and those two facts decide everything else. A 3 by 2 metre slab 100 millimetres thick is 0.6 of a cubic metre of wet concrete, which on a 1:2:4 mix is about 200 kilograms of cement, 277 litres of sand and 554 litres of coarse aggregate. This calculator gives the wet volume with your own waste allowance, the weight, and the dry ingredients broken out by part.

At a glance

What you enter
Length, Width, Thickness, Waste allowance, Cement part, Sand part, Coarse aggregate part, Dry volume factor, Bulk density of cement, Cement bag size, Price per bag of cement
What you get
Concrete to order, Weight of the concrete, Cement bags to buy, Cement by weight, Sand, Coarse aggregate, Area of the slab, Cost of the cement
Formula shown
Yes, every step, right below your results.
Cost and privacy
Free, no account needed, and nothing you type is stored.

See worked examples โ†“ Read the FAQ โ†“ Share this calculator โ†“

The longer dimension of the slab, footing or pad.

The other dimension, at right angles to the length.

75 to 100 mm for a path, 100 to 150 mm for a shed base. A slab that carries a vehicle needs a thickness that has been specified.

Five per cent on a flat slab over a prepared base, ten per cent in a rough trench or over hardcore.

Cement part

The first number of the mix ratio. A 1:2:4 mix uses 1 part cement.

Sand part

The middle number of the mix ratio. Sharp sand is the usual fine aggregate.

Coarse aggregate part

The last number of the mix ratio. 20 mm crushed stone is the usual coarse aggregate.

Loose sand and stone contain air that the cement paste fills, so the dry ingredients bulk up. The standard allowance is 1.54 times the wet volume.

Turns the volume of cement into the weight the bag is sold by. About 1440 kilograms per cubic metre for ordinary Portland cement.

25 kg is the common bag in the UK and Europe, 50 kg in the US, and 20 kg in some ranges.

Optional. Used for the cement cost only, not for the sand or the stone.

Reset

Results are estimates for general information only, always verify with a professional or official source before acting on them.

How to use the Concrete Calculator

  1. 1 Enter Length (mm), The longer dimension of the slab, footing or pad.
  2. 2 Enter Width (mm), The other dimension, at right angles to the length.
  3. 3 Enter Thickness (mm), 75 to 100 mm for a path, 100 to 150 mm for a shed base. A slab that carries a vehicle needs a thickness that has been specified.
  4. 4 Enter Waste allowance (%), Five per cent on a flat slab over a prepared base, ten per cent in a rough trench or over hardcore.
  5. 5 Enter Cement part, The first number of the mix ratio. A 1:2:4 mix uses 1 part cement.
  6. 6 Enter Sand part, The middle number of the mix ratio. Sharp sand is the usual fine aggregate.
  7. 7 Enter Coarse aggregate part, The last number of the mix ratio. 20 mm crushed stone is the usual coarse aggregate.
  8. 8 Enter Dry volume factor (times), Loose sand and stone contain air that the cement paste fills, so the dry ingredients bulk up. The standard allowance is 1.54 times the wet volume.
  9. 9 Enter Bulk density of cement (kg/m3), Turns the volume of cement into the weight the bag is sold by. About 1440 kilograms per cubic metre for ordinary Portland cement.
  10. 10 Enter Cement bag size (kg), 25 kg is the common bag in the UK and Europe, 50 kg in the US, and 20 kg in some ranges.
  11. 11 Enter Price per bag of cement, Optional. Used for the cement cost only, not for the sand or the stone.
  12. 12 Press Calculate. You get Concrete to order, Weight of the concrete, Cement bags to buy, Cement by weight, Sand, Coarse aggregate, Area of the slab, Cost of the cement, and every intermediate step stays visible under "How is this calculated?"
  13. 13 Change one number at a time to see what moves the result, that is usually the most useful thing a calculator can tell you.

Worked examples

Real numbers run through this calculator. Open any example to load it into the form above and change it.

A garden path in 1:2:4

A 3000 by 2000 millimetre path, 100 millimetres thick, with five per cent waste.

You enter

Length
3,000 mm
Width
2,000 mm
Thickness
100 mm
Waste allowance
5%
Cement part
1
Sand part
2
Coarse aggregate part
4
Dry volume factor
1.54 times
Bulk density of cement
1,440 kg/m3
Cement bag size
25 kg
Price per bag of cement
$0.00

You get

Concrete to order
0.63 m3
Weight of the concrete
1.51 t
Cement bags to buy
8
Cement by weight
199.58 kg
Sand
277.20 litres
Coarse aggregate
554.40 litres
Area of the slab
6.00 m2
Cost of the cement
$0.00

Six square metres and 0.6 of a cubic metre of wet concrete, which is 0.63 with the waste allowance and 1.51 tonnes. The dry ingredients come to 0.97 of a cubic metre, so 200 kilograms of cement, which is 8 bags of 25 kilograms, plus 277 litres of sand and 554 litres of stone.

Open this example in the calculator โ†’

A shed base in 1:2:4 with ten per cent waste

A 4000 by 3000 millimetre base, 100 millimetres thick, over a rough excavated base.

You enter

Length
4,000 mm
Width
3,000 mm
Thickness
100 mm
Waste allowance
10%
Cement part
1
Sand part
2
Coarse aggregate part
4
Dry volume factor
1.54 times
Bulk density of cement
1,440 kg/m3
Cement bag size
25 kg
Price per bag of cement
$0.00

You get

Concrete to order
1.32 m3
Weight of the concrete
3.17 t
Cement bags to buy
17
Cement by weight
418.18 kg
Sand
580.80 litres
Coarse aggregate
1,161.60 litres
Area of the slab
12.00 m2
Cost of the cement
$0.00

Twelve square metres and 1.2 cubic metres of wet concrete, which is 1.32 with the waste allowance and 3.17 tonnes. That needs 418 kilograms of cement, so 17 bags of 25 kilograms, with 581 litres of sand and 1162 litres of stone. The cement works out at 317 kilograms per cubic metre, which is the published figure for this mix.

Open this example in the calculator โ†’

A strip footing in a leaner 1:3:6

A 10 metre strip footing 600 millimetres wide and 200 millimetres deep, with ten per cent waste.

You enter

Length
10,000 mm
Width
600 mm
Thickness
200 mm
Waste allowance
10%
Cement part
1
Sand part
3
Coarse aggregate part
6
Dry volume factor
1.54 times
Bulk density of cement
1,440 kg/m3
Cement bag size
25 kg
Price per bag of cement
$0.00

You get

Concrete to order
1.32 m3
Weight of the concrete
3.17 t
Cement bags to buy
12
Cement by weight
292.72 kg
Sand
609.84 litres
Coarse aggregate
1,219.68 litres
Area of the slab
6.00 m2
Cost of the cement
$0.00

The same 1.32 cubic metres of concrete, but the leaner mix spreads the dry ingredients over ten parts instead of seven, so the cement drops to 293 kilograms, which is 12 bags of 25 kilograms, while the sand and stone rise to 610 and 1220 litres. Twelve bags instead of seventeen for the same volume is what mass fill mixes are for.

Open this example in the calculator โ†’

Frequently asked questions

How much concrete do I need for a slab?
Multiply the length by the width by the thickness, all in metres, to get cubic metres. A slab 3 metres by 2 metres at 100 millimetres thick is 3 times 2 times 0.1, which is 0.6 of a cubic metre. Add a waste allowance of five per cent on a flat prepared base or ten per cent in a rough trench, which brings that slab to about 0.63 of a cubic metre. Ready mix is ordered to the tenth of a cubic metre, so you would order 0.7.
What does a 1:2:4 mix mean?
It means one part cement, two parts sand and four parts coarse aggregate, measured by volume rather than by weight. A bucket, a barrow or a shovel all work as the measure as long as the same one is used for every part, because the ratio is what matters and not the size of the container. Adding the parts gives seven, and each ingredient takes its own share of the dry volume, so on 1:2:4 the cement is one seventh of the dry ingredients. It is a nominal mix, which is a site convention, and not the same thing as a designed mix for structural work.
How many bags of cement are in a cubic metre of concrete?
On a 1:2:4 mix, a cubic metre of finished concrete needs about 317 kilograms of cement, which is about 13 bags of 25 kilograms or 7 bags of 50 kilograms. The figure is higher than people expect because the dry ingredients bulk up: the 1.54 dry volume factor turns 1 cubic metre of wet concrete into about 1.54 cubic metres of loose sand, stone and cement. A leaner 1:3:6 mix drops the cement to roughly 222 kilograms per cubic metre, which is why mass fill and blinding are mixed lean.
How much water goes into the mix?
The usual starting point is a water to cement ratio of about 0.5 by weight, so 200 kilograms of cement takes roughly 100 litres of water. That is a starting point rather than a rule, because damp sand and wet stone already carry water into the mix, and adding the full amount to a wet aggregate produces a soupy mix. Water is what makes concrete workable, and it is also what makes it weak: extra water raises the ratio, lowers the strength and increases shrinkage cracking. A mix that stands on a shovel is about right for general work.
Should I order ready mix or mix it myself?
Bag mixing is practical up to about half a cubic metre, which is roughly 40 to 50 bags of ballast plus the cement and a great deal of shovelling. Above that, ready mix is usually the better answer even though it is priced by the cubic metre with a minimum load and often a part load charge, because the labour of mixing a cubic metre by hand is a full day and the result is less consistent. The break even sits lower if the concrete has to be placed quickly, or if a cold joint between two pours would be a problem.

More money questions answered โ†’

Share this tool

Send the calculator, or your exact numbers, to whoever needs to see them.

Your browser blocked the clipboard, select the link above and copy it manually.

Embed this calculator on your own site โ†’

We use essential cookies to run this site. Optional partners (advertising and analytics) only load if you accept them. See our Privacy Policy.